Deconstruction of a black baking line no. 2: the baking line consists of a chimney (H=75 m), flat granulator building consisting of reinforced concrete beams, pillars and ceilings, 2 electrofilter units, 140 m long rotary kiln with a diameter of 5.50 m, refractory inner cladding and a cooling grid. The flat granulator building was cut into 6 parts using electrical equipment equipped with diamond-dressed wire: each cut element (beams-ceilings and pillars) was removed by means of a 300 T tracked crane (element weight 140 T) and placed on the ground for subsequent demolition with an excavator equipped with a hydraulic crusher.

1) Deconstruction of 2 metal silos (H=40 m) connected to the baking line no. 4: the baking line. The silos were deconstructed into 2 by means of oxypropanic torches: each deconstructed element was removed with a 200 T crane (element weight 50 T) and positioned on the ground for subsequent demolition with an excavator equipped with hydraulic shears.

2) Controlled demolition by means of a fly-system of the production bucket lift on the baking line no. 4 (H=45 mt)
The fly-system was lifted by a crane (200 T) and remote controlled by an operator working at height in lifting platform basket

Deconstruction of no. 2 metal chimneys (H=100 m);

The chimneys were deconstructed by means of oxypropane torches: each cut element was removed with a tracked crane and positioned on the ground for subsequent demolition with an excavator equipped with hydraulic shears.

Deconstruction of a chimney stack in a hydroelectric station in Villa di Serio (H=100 m): the chimney was cut using electrical equipment equipped with diamond-dressed wire placed on electric self-climbing scaffolding; each cut element was removed by means of crane and placed on the ground for subsequent demolition with an excavator equipped with a hydraulic crusher.

Deconstruction of a chimney (H=102 m): the cutting process was carried out using electrical equipment with diamond-dressed wire positioned on electric self-climbing scaffolding.

Controlled demolition by means of a super-long excavator of plant systems and sections of the areas housing the former lime furnaces and lime hoppers (H=48 m).